Official TranscriptOfficial Journal EN of the European Union L series 2026/1470 11.9.2026 COMMISSION DELEGATED REGULATION(EU) 2026/1470 of 2 July 2026 amending Delegated Regulation (EU) 2022/2202 by updating the list of selected cross-border projects in the field of renewable energy (Text with EEA relevance) THE EUROPEAN COMMISSION, Having regard to the Treaty on the Functioning of the European Union, Having regard...
Official Journal EN of the European Union L series 2026/1470 11.9.2026 COMMISSION DELEGATED REGULATION(EU) 2026/1470 of 2 July 2026 amending Delegated Regulation (EU) 2022/2202 by updating the list of selected cross-border projects in the field of renewable energy (Text with EEA relevance) THE EUROPEAN COMMISSION, Having regard to the Treaty on the Functioning of the European Union, Having regard to Regulation (EU) 2021/1153 of the European Parliament and of the Council of 7 July 2021 establishing the Connecting Europe Facility and repealing Regulations (EU) No 1316/2013 and (EU) No 283/2014(1), and in particular Article 25(1), point (b), thereof,
Whereas:
(1) Regulation (EU) 2021/1153 establishes a category of cross-border projects in the field of renewable energy that contribute to decarbonisation, to completing the internal energy market and to improving the security of energy supply. Pursuant to Article 7(1) of Regulation (EU) 2021/1153, those cross-border projects are set up by a cooperation agreement between two or more Member States or between one or more Member States and one or more third countries, as set out in Articles 8, 9, 11 and 13 of Directive (EU) 2018/2001 of the European Parliament and of the Council(2).
(2) The selection of cross-border projects in the field of renewable energy is subject to the general criteria and procedures set out in Regulation (EU) 2021/1153 and to further specific selection criteria and details of the selection process set out in Commission Delegated Regulation (EU) 2022/342(3).
(3) Cross-border projects in the field of renewable energy are selected and included in a list drawn up for this purpose by means of delegated acts.
(4) The inclusion of cross-border projects in the field of renewable energy in the list makes them eligible to apply for funding under the Connecting Europe Facility.
(5) Following a call for proposals published on 2 September 2025 and closed on 5 February 2026, three new renewable energy cross-border projects were selected. The selected projects were assessed by external experts and by experts from the European Climate, Infrastructure and Environment Executive Agency and the European Commission. The assessment examined in particular the cost-effective exploitation of renewable energy and implementation of the projects through different renewable energy technologies, including geothermal energy, onshore wind and solar photovoltaic.
(6) The Commission notified the assessment results relating to the selected new renewable energy cross-border projects to the Expert Group for renewable energy cross-border projects(4)(‘the Expert Group’). Following the agreement of the Expert Group, the selected new renewable energy cross-border projects should be included in the list.
(7) The inclusion of projects in the list of renewable energy cross-border projects is subject to their compliance with Union law, including with the outcome of the relevant environmental assessment and permit procedures.
(1) OJ L 249, 14.7.2021, p. 38, ELI: http://data.europa.eu/eli/reg/2021/1153/oj.
(2) Directive (EU) 2018/2001 of the European Parliament and of the Council of 11 December 2018 on the promotion of the use of energy from renewable sources (OJ L 328, 21.12.2018, p. 82, ELI: http://data.europa.eu/eli/dir/2018/2001/oj).
(3) Commission Delegated Regulation (EU) 2022/342 of 21 December 2021 supplementing Regulation (EU) 2021/1153 of the European Parliament and of the Council with regard to the specific selection criteria and the details of the process for selecting cross-border projects in the field of renewable energy (OJ L 62, 1.3.2022, p. 1, ELI: http://data.europa.eu/eli/reg_del/2022/342/oj).
(4) Referred to in Part IV, point 4(b), of the Annex to Regulation (EU) 2021/1153, and further specified in Delegated Regulation
(EU) 2022/342.
ELI: http://data.europa.eu/eli/reg_del/2026/1470/oj 1/3EN OJ L, 11.9.2026
(8) For the purposes of implementing Part IV, point 4(h), of the Annex to Regulation (EU) 2021/1153, the Commission submitted to the Expert Group the annual progress report on the projects already in the list of cross-border projects in the field of renewable energy. The progress report identified one project for which implementation will not be continued in its current cross-border configuration due to significant challenges and uncertainties. Following the agreement of the group, that renewable energy cross-border project should be withdrawn from the list.
(9) Commission Delegated Regulation (EU) 2022/2202(5)should therefore be amended accordingly,
HAS ADOPTED THIS REGULATION:
Article 1 Article 1 of Delegated Regulation (EU) 2022/2202 is replaced by the following: ‘Article 1 The list of cross-border projects in the field of renewable energy selected pursuant to Part IV, point 4(g), of the Annex to Regulation (EU) 2021/1153 shall be as follows:
Project number Project name Project developers Participating countries 2022-05 ELWIND – Estonian Latvian joint Ministry of Economic Estonia and Latvia hybrid offshore wind project Affairs and Communications of Estonia; The Ministry of Economics of the Republic of Latvia 2022-07 CICERONE – CEO-Alliance Cross- Essent Hydrogen B.V.; Germany, the Netherlands, Border-European Green Hydrogen IBERDROLA CLIENTES and Spain Value Chain S.A.U.
2022-10 UNITED HEAT – Climate-neutral Stadtwerke Görlitz AG; Germany and Poland district heating in the European SEC Zgorzelec Sp. z o.o. city Goerlitz Zgorzelec – 2023-2 ULP-RES WP – Utilitas Lode- Utilitas Wind SIA; Utilitas Estonia and Latvia Penuja RES Wind park Wind OÜ 2023-3 SLOWP – Saare-Liivi Offshore Utilitas Wind OÜ Estonia and Luxembourg Wind Park 2023-6 TMNHSA – Turnu Magurele – Natsionalna Elektricheska Bulgaria and Romania Nikopol Hydraulic Structures Kompania EAD;
Assembly S.P.E.E.H.
HIDROELECTRICA S.A.
2023-7 BEI – Bornholm Energy Island Ministry of Climate, Energy Denmark and Germany and Utilities
(5) Commission Delegated Regulation (EU) 2022/2202 of 29 August 2022 supplementing Regulation (EU) 2021/1153 of the European Parliament and of the Council by establishing a list of selected cross-border projects in the field of renewable energy (OJ L 293,
14.11.2022, p. 1, ELI: http://data.europa.eu/eli/reg_del/2022/2202/oj).
2/3 ELI: http://data.europa.eu/eli/reg_del/2026/1470/ojEN OJ L, 11.9.2026 Project number Project name Project developers Participating countries 2024-1 CORES – Comprehensive DGEG – Direção Geral de Luxembourg and Portugal Offshore Renewable Energy Energia e Geologia Potential Studies 2024-2 Medlink Renewable Generation – Zhero Europe B.V: Private Algeria, Italy and Tunisia MedGen legal entity in MS (NL – coordinator) Medlinks Algeria B.V.:
Private legal entity in MS (NL – promoter) Medlinks Tunisia B.V Private legal entity in a MS (NL – promoter) 2024-3 Utilitas Eleja-Joniski Wind Park – Utilitas Wind SIA; Latvia and Lithuania UELJO WP Utilitas Wind UAB 2024-4 LiiviBay Offshore Wind park Enefit Green AS Estonia and Latvia 2024-6 Green transformation of district SEC Region Sp. z o.o and Germany and Poland heating in the twin cities of Stadtwerke Frankfurt Słubice & Frankfurt (Oder) – Twin (Oder) GmbH Heat 2025-2 Wind Integration for Network DTEK Romania and Ukraine Decarbonization – WIND 2025-4 Decarbonization of Industrial ENERTRAG SE Germany and Poland Clusters at the Polish German Border Region via the Deployment of an Integrated Cross-Border Power Plant – DEPLOY 2025-5 Zero Emission heat network Geothermie- Austria and Germany’ linking Germany and Austria – Wärmegesellschaft ZEGA-LINNK Braunau-Simbach mbH Article 2 This Regulation shall enter into force on the twentieth day following that of its publication in the Official Journal of the European Union.
This Regulation shall be binding in its entirety and directly applicable in all Member States.
Done at Brussels, 2 July 2026.
For the Commission The President Ursula VON DER LEYEN
ELI: http://data.europa.eu/eli/reg_del/2026/1470/oj 3/3