Official Gazette Notification Text
Official TranscriptStatus: This is the original version (as it was originally made). This item of legislation is currently only available in its original format. STATUTORY INSTRUMENTS 2026 No. 243 ELECTRICITY The Energy-Intensive Industry Electricity Support Payments and Levy (Amendment) Regulations 2026 Made - - - - 5th March 2026 Coming into force - - 1st April 2026 The Secretary of State makes these Regulations...
Status: This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
STATUTORY INSTRUMENTS 2026 No. 243 ELECTRICITY The Energy-Intensive Industry Electricity Support Payments and Levy (Amendment) Regulations 2026 Made - - - - 5th March 2026 Coming into force - - 1st April 2026 The Secretary of State makes these Regulations in exercise of the powers conferred by sections 211(1) to (3) and (5) and 212(1) and (2) of the Energy Act 2023(1).
In accordance with sections 211(11), 212(10) and 331(3) of the Energy Act 2023, a draft of these Regulations has been laid before, and approved by a resolution of, each House of Parliament.
Citation, commencement and extent
1.โ(1) These Regulations may be cited as the Energy-Intensive Industry Electricity Support Payments and Levy (Amendment) Regulations 2026.
(2) These Regulations extend to England and Wales and Scotland.
(3) These Regulations come into force on 1st April 2026.
Amendments
2.โ(1) The Energy-Intensive Industry Electricity Support Payments and Levy Regulations 2024(2) are amended as set out in paragraphs (2) to (4).
(2) In regulation 7(1), for โone monthโ substitute โtwo monthsโ.
(3) In regulation 8(2), for โ60%โ substitute โ90%โ.
(4) In regulation 13(2), for โ60%โ substitute โ90%โ.
(1) 2023 c. 52.
(2) S.I. 2024/409.Document Generated: 2026-04-01
Status: This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
Chris McDonald Minister for Industry 5th March 2026 Department for Business and Trade 2Document Generated: 2026-04-01
Status: This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
EXPLANATORY NOTE (This note is not part of the Regulations) These Regulations amend the Energy-Intensive Industry Electricity Support Payments and Levy Regulations 2024 (S.I. 2024/409) (โthe 2024 Regulationsโ). The 2024 Regulations entitle eligible energy-intensive businesses to electricity support payments in respect of network charging costs and set out how such payments are to be funded (through a levy on electricity suppliers).
Regulation 2(2) increases the period for making an application from one month to two months.
The amendments made by regulation 2(3) and (4) have the effect of increasing the level of support payments from 60% to 90% of network charges. Regulation 2(3) increases the size of the estimated levy fund and regulation 2(4) increases the level of EII support payments for the claim month.
An impact assessment setting out the key impacts of this policy has been completed.
The impact assessment is published with the Explanatory Memorandum alongside this instrument on www.legislation.gov.uk. A copy is also available by contacting EII.correspondence@businessandtrade.gov.uk or the Department for Business and Trade, Old Admiralty Building, Admiralty Place, London, SW1A 2DY.
3