GOVERNMENT OF INDIA
MINISTRY OF STEEL
LOK SABHA
UNSTARRED QUESTION NO. 2681
FOR ANSWER ON 04.08.2026
PERFORMANCE APPRAISAL OF MECON
2681. SHRI RAJEEV RAI:
Will the Minister of STEEL be pleased to state:
(a) the details of the financial performance of the MECON including turnover,
profit/loss, order book and net worth during the last five years, year-wise;
(b) whether it has incurred losses during...
GOVERNMENT OF INDIA MINISTRY OF STEEL LOK SABHA UNSTARRED QUESTION NO. 2681 FOR ANSWER ON 04.08.2026 PERFORMANCE APPRAISAL OF MECON
2681. SHRI RAJEEV RAI:
Will the Minister of STEEL be pleased to state:
(a) the details of the financial performance of the MECON including turnover, profit/loss, order book and net worth during the last five years, year-wise;
(b) whether it has incurred losses during the current financial year and if so, the reasons therefor;
(c) the value of projects awarded, projects completed on schedule and delayed, reasons for delays during the last five years, year-wise;
(d) whether any major projects have been transferred to private agencies due to performance issues and if so, the details thereof; and
(e) the details of manpower position, vacancies, recruitments, reasons for non- appointment of a regular Chairman and the status of proposals for recruitment, etc., cadre-wise? ANSWER THE MINISTER OF STATE IN THE (SHRI BHUPATHIRAJU SRINIVASA VARMA) MINISTRY OF STEEL
(a)&(b): Details of the financial performance of MECON Limited including turnover, profit/loss, order book and net worth during the last five years are as under:- (Rs. In Crores) Description FY 2021-22 FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 Turnover 586.67 854.97 923.79 1,073.82 1,514.78 PBT 19.54 34.01 77.62 32.08 104.53 PAT 13.70 31.01 54.56 28.22 78.45
Order Book 1,096.55 235.29 962.45 1,799.22 1,183.76 Net Worth 431.75 399.34 445.77 465.67 535.42 The MECON Limited has not incurred any loss during Financial Year 2025-26.
Contdโฆ..2/-::2::
(c) The details of Engineering, Procurement, and Construction (EPC) Projects awarded to MECON Limited during the last five years along with their completion
status are as under: - Year Projects On time Projects delayed, if any Value of Projects awarded (in lakhs) 2025-26 Nil -- -- -- 2024-25 3 2 1, Delayed due to 1,06,582.65 technical issues 2023-24 2 1 1, Delayed due to 65,914.6 geopolitical crisis and middle east war.
2022-23 Nil -- -- -- 2021-22 2 0 2, Delayed due to late 27,451.38 handling over of lands and fronts of the site.
(d) No, Sir.
(e) MECON Limited has regular Chairman & Managing Director. The total manpower strength of MECON Limited, comprising executives and non-executives, is 977 employees. As on date, 89 posts are vacant. *****