Official Gazette Notification Text
Official Transcriptरजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99 ससीी..जजीी..--डडीी..एएलल..--अअ..--0044007722002255--226644337777 xxxGIDHxxx CCGG--DDLL--EE--0044007722002255--226644337777 xxxGIDExxx असाधारण EXTRAORDINARY भाग III—खण् ड 4 PART III—Section 4 प्राजधकार स ेप्रकाजित PUBLISHED BY AUTHORITY स.ं 473] नई दिल्ली, बुधवार, िुलाई 2, 2025/आषाढ़ 11, 1947 No. 473] NEW DELHI, WEDNESDAY, JULY 2, 2025/ASHADHA...
रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99 ससीी..जजीी..--डडीी..एएलल..--अअ..--0044007722002255--226644337777 xxxGIDHxxx CCGG--DDLL--EE--0044007722002255--226644337777 xxxGIDExxx असाधारण EXTRAORDINARY भाग III—खण् ड 4 PART III—Section 4 प्राजधकार स ेप्रकाजित PUBLISHED BY AUTHORITY स.ं 473] नई दिल्ली, बुधवार, िुलाई 2, 2025/आषाढ़ 11, 1947 No. 473] NEW DELHI, WEDNESDAY, JULY 2, 2025/ASHADHA 11, 1947 .—dsUæh; fo|qr fofu;ked vk;ksx] fo|qr vf/kfu;e] 2003 /kkjk 178 ds v/khu çnÙk 'kfä;ks a rFkk bl fufeÙk lkeFkZ~;dkjh lHkh vU; 'kfä;ks a dk ç;ksx djrs gq, rFkk iwoZ çdk'ku ds ckn] dsUæh;
fo|qr fofu;ked vk;ksx ¼fopyu O;oLFkkiu ra= ,oa lac) ekeys½ fofu;e] 2024 ¼ftls blds i'pkr~ Þeyw fofu;eß dgk x;k gS½ dks la'kksf/kr dju s ds fy, ,rn~ }kjk fuEufyf[kr fofu;e cukrk gS] vFkkZr~%&
1.
1.1 bu fofu;eks a dk laf{kIr uke dsUæh; fo|qr fofu;ked vk;ksx ¼fopyu O;oLFkkiu ra= ,oa lac) ekeys½ ¼nlw jk la”kks/ku½ fofu;e] 2025 gSA
1.2 ;s fofu;e 01-07-2025 ls ço`Ùk gksxa sA
2.
2.1 eyw fofu;e d s fofu;e 8 ds [k.M ¼8½ dks fuEukuqlkj izfrLFkkfir fd;k tk,xk% “(8) v”kDr fo|qr d svra%{ksi.k ds fy, izHkkj -
(1) v”kDr fo|qr d svar%{ksi.k d sfy, izHkkj] bl fofu;e d s[k.M ¼2½ vkSj [k.M ¼3½ d sv/khu fofufnZ’V ekeyksa dks NksM+dj “kwU; gksaxs:
4357 GI/2025 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4]
(2) FkeZy mRiknu LVs”kuksa ds ekeys es]a ;wfuV ds izFke flaØkWukbts”ku dh rkjh[k ls lQyrkiowZd Vªk;y ju iwjk gksus rd fxzM eas var%{ksfir v”kDr fo|qr #-2-86@fdyksokV ?k.Vs dh lhek ds v/;/khu] izR;sd le; CykWd d sfy, fopyuk sa ds fy, izHkkjksa dh @ lkekU; nj vnk dh tk,xhA
(3) ;fn v”kDr fo|qr fxzM dksM eas ;FkkfofufnZ’V lQy Vªk;y ju ds ckn vuqlwfpr dh tkrh gS rks vuqlwfpr v”kDr fo|qr ij fopyu ds fy, çHkkj lkekU; foØsrk ;k MCY;,wl foØrsk] ;FkkfLFkfr] ds fy, ;Fkk ykx wgksxa sA
(4) bl fofu;e d s[k.M ¼2½ vkSj [k.M ¼3½ d smic/akks ads gksrs gq, Hkh] tc iz.kkyh fÝDosla h] ,Q > 50-05 gV~Zt +gS rks v”kDr fo|qr d svra%{ksi.k ds fy, ;k lkekU; foØrsk ;k MCY;,wl foØrsk] ;FkkfLFkfr] }kjk vf/kd vra%{ksi.k d sek/;e ls lQy Vªk;y ju d sckn vuqlwfpr v”kDr fo|qr d sfopyu d sfy, izHkkj “kwU; gksxa As** gjçhr flag çqFkh, lfpo [जवज्ञापन-III/4/असा./206/2025-26] :
(i) dsUnzh; fo|qr fofu;ked vk;ksx ¼fopyu O;oLFkkiu r=a ,oa lac) ekey½s fofu;e] 2024 fnukad 21-08-2024 dks Hkkjr ds jkti= ¼vlk/kkj.k½ la- 642 ds Hkkx III] [kaM 4 eas çdkf'kr gq, FksA
(ii) dsUnzh; fo|qr fofu;ked vk;ksx ¼fopyu O;oLFkkiu r=a ,oa lac) ekey½s ¼çFke la”kks/ku½ fofu;e] 2024 fnukad 24-12-2024 dk s Hkkjr ds jkti= ¼vlk/kkj.k½ la- 1030 ds Hkkx III] [kaM 4 eas çdkf'kr gq, FksA CENTRAL ELECTRICITY REGULATORY COMMISSION
NOTIFICATION New Delhi, the 25th June, 2025 No. L-1/260/2021/CERC.—In exercise of the powers conferred under Section 178 of the Electricity Act, 2003 and all other powers enabling it in this behalf and after previous publication, the Central Electricity Regulatory Commission, hereby makes the following regulations, to amend the Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2024 (hereinafter referred to as the "Principal Regulations") namely: -
1. Short Title And Comments
1.1 These regulations may be called the Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) (Second Amendment) Regulations, 2025.
1.2 These regulations shall come into force with effect from 01.07.2025.
2. Amendment Of Regulation 8 (Charges For Deviations) Of The Principal Regulations:
2.1 Clause (8) of Regulation 8 of the Principal Regulations shall be substituted as under: “(8) Charges for injection of infirm power -
(1) The charges for injection of infirm power shall be zero, except in cases specified under clauses (2) and (3) of this Regulation:
(2) In case of thermal generating stations, the infirm power injected into the grid from the date of first synchronization of the unit up to the successful completion of the trial run shall be paid @ Normal Rate of Charges for Deviations for each time block, subject to a ceiling of ₹ 2.86/kWh.[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 3
(3) If infirm power is scheduled after a successful trial run as specified in the Grid Code, the charges for deviation over the scheduled infirm power shall be as applicable for a general seller or WS seller, as the case may be.
(4) Notwithstanding the provisions of clauses (2) and (3) of this Regulation, when the system frequency, f > 50.05Hz, the charges for injection of infirm power or for deviation of scheduled infirm power after the successful trial run by way of over injection by a general seller or WS seller, as the case may be, shall be zero.” HARPREET SINGH PRUTHI, Secy.
[Advt.-III/4/Exty./206/2025-26]
Note:
(i) The Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2024 were published in Part III, Section 4, No. 642 of the Gazette of India (Extraordinary) dated 21.08.2024.
(ii) The Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) (First Amendment) Regulations, 2024 were published in Part III,
Section 4, No. 1030 of the Gazette of India (Extraordinary) dated 24.12.2024.