Date: 25th March 2025
Category: Extra Ordinary
New Delhi

Read or download the official PDF of this gazette notification issued by the Central Electricity Regulatory Commission on 25th March 2025. Classified under Extra Ordinary.

Official Gazette Notification Text

Official Transcript

रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99 सी.जी.-डी.एल.-अ.-25032025-261941 xxxGIDHxxx CG-DL-E-25032025-261941 xxxGIDExxx असाधारण EXTRAORDINARY भाग III—खण् ड 4 PART III—Section 4 प्राजधकार स ेप्रकाजित PUBLISHED BY AUTHORITY स.ं 238] नई दिल्ली, मगं लिार, मार् च25, 2025/र्त्रै 4, 1947 No. 238] NEW DELHI, TUESDAY, MARCH 25, 2025/CHAITRA 4, 1947 ubZ fnYyh] 5 ekpZ] 2025 .—Þforj.k...

PolicyIndex Takeaway
Get AI summary →
  • The Central Electricity Regulatory Commission (CERC) has notified the escalation rates applicable for February 2025 for the purpose of payment for power procured by distribution licensees.
  • These rates are applicable as per the Power Purchase Agreements (PPAs) entered into under the guidelines for long-term procurement of electricity from thermal power stations.
  • The notification specifies the monthly escalation rates for imported coal, transportation of imported coal, and inland handling of imported coal.
  • The escalation rate for imported coal is negative 3.85%.
  • The escalation rate for transportation of imported coal is 6.23%.