Official TranscriptGOVERNMENT OF INDIA MINISTRY OF NEW AND RENEWABLE ENERGY LOK SABHA STARRED QUESTION NO. 152 ANSWERED ON 29.07.2026 ROOFTOP SOLAR INSTALLATIONS UNDER PM-SGMBY 152. SHRI RAMASAHAYAM RAGHURM REDDY Will the Minister of NEW AND RENEWABLE ENERGY be pleased to state: (a) the targets set and achieved for household rooftop solar installations under the Pradhan Mantri-Surya Ghar Muft Bijli Yojana (PM-SGMBY)...
GOVERNMENT OF INDIA MINISTRY OF NEW AND RENEWABLE ENERGY LOK SABHA STARRED QUESTION NO. 152 ANSWERED ON 29.07.2026 ROOFTOP SOLAR INSTALLATIONS UNDER PM-SGMBY
152. SHRI RAMASAHAYAM RAGHURM REDDY
Will the Minister of NEW AND RENEWABLE ENERGY be pleased to state:
(a) the targets set and achieved for household rooftop solar installations under the Pradhan Mantri-Surya Ghar Muft Bijli Yojana (PM-SGMBY) since its launch, year and State-wise including Chhattisgarh;
(b) the total number of households with solarised rooftops under the PM-SGMBY, rooftop solar, capacity-wise (1-2 kW, 2-3 kW, 3 kW and above), State/UT and district-wise including Chhattisgarh;
(c) the total number of loan applications sanctioned and disbursed for rooftop solar installations under the yojana along with the total loan amount sanctioned and disbursed in each category till date, State/UT-wise including district-wise for Chhattisgarh;
(d) whether the Government has assessed the average monthly reduction in electricity bills achieved by households under the yojana and if so, the details thereof, State/UT-wise including Chhattisgarh;
(e) whether the Government is on track to achieve the target of rooftop solar installations in one crore households by the year 2026-27 and if so, the details thereof; and
(f) the collaborative steps being taken by the Government with the State power distribution utility to expedite technical feasibility approvals and net-metering installations for rural consumers? ANSWER THE MINISTER OF NEW & RENEWABLE ENERGY, CONSUMER AFFAIRS & FOOD AND PUBLIC DISTRIBUTION AND EDUCATION.
(SHRI PRALHAD JOSHI)
(a) to (f) A statement is laid on the table of the house. *****Statement referred to in reply of parts (a) to (f) of Lok Sabha Starred Question No. 152 to be answered on 29.07.2026 regarding Rooftop Solar Installations under PM-SGMBY
(a) & (b): The Ministry of New and Renewable Energy (MNRE) has been implementing the
PM Surya Ghar: Muft Bijli Yojana (PMSG: MBY) since February 2024, aiming to install rooftop solar (RTS) systems in one crore residential households across the country by FY 2026–27 with a total financial outlay of Rs. 75,021 crores.
The PMSG: MBY is a demand-driven scheme wherein all residential consumers in the country, including those in the state of Chhattisgarh, having a grid-connected electricity connection with the local DISCOM, can avail the benefits of the scheme, for installation of RTS systems by applying on the National Portal (www.pmsuryaghar.gov.in) of the scheme.
Under the scheme, since its launch in February 2024, a total of 40,07,355 RTS systems have been installed, benefitting 48,21,986 households across the country as on 24.07.2026. The RTS capacity-wise total number of households solarised under the PM-SGMBY, is given below:
RTS capacity RTS systems Households Benefitted installed (Nos.) (Nos.) Upto 2 kWp 68,857 77,742 2 – 3 kWp 3,41,066 3,48,641 (Greater than 2 kWp and upto 3 kWp) > 3 kWp 35,97,361 43,95,603 Total 40,07,284 48,21,986 The State/UT-wise details are given in the Annexure I and the district-wise details for the state of Chhattisgarh are given in the Annexure II.
(c) Under the scheme, since its launch in February 2024, a total of 21,31,331 loan applications with the total loan amount of Rs 39,930 have been sanctioned and 18,82,853 loan applications with the total loan amount of Rs 31,652 have been disbursed for RTS systems installations across the country. The RTS capacity-wise details is given below:RTS capacity loan loan amount loan loan (in KW) applications sanctioned applications amount sanctioned (Rs. Cr) disbursed disbursed (Nos.) (Nos.) (Rs. Cr) Upto 2 kWp 69,520 915 58,209 678 2 – 3 kWp (Greater than 2 kWp and upto 3 kWp) 1,461,518 26,915 1,290,161 21,289 Above 3 kWp 600,293 12,100 534,483 9,685 Total 21,31,331 39,930 18,82,853 31,652 The RTS capacity-wise & State/UT-wise details are given in the Annexure III and the district- wise details for the state of Chhattisgarh are given in the Annexure IV.
(d): While the electricity bills of consumers installed RTS under the scheme have been largely reduced, over 18.93 lakh beneficiaries have been reported by DISCOMs across the country, including the rural households, to receive zero electricity bill after installation of RTS systems under the scheme during any month/billing period, depending on their self-consumption of electricity. The state/UT-wise details are given in Annexure V.
(e) & (f): The pace of implementation of the scheme is increasing. During the initial phase, it took a few months to cover RTS installations for one lakh households, and now, for the same coverage, it takes around 7 days. To further ensure timely achievement of the overall RTS installations target, expedite technical feasibility approvals and net-metering installations across the country, including in the state of Chhattisgarh, the Ministry has taken the following
measures: • Online process from application to subsidy disbursement directly into the residential consumer's bank account through the National Portal. • Availability of collateral-free loan from nationalized banks at a concessional interest rate of repo-rate plus 50 bps, i.e., 5.75% per annum for the present, with a tenure of 10 years.
• Simplified the regulatory approval process by waiving the technical feasibility requirement and introducing auto load enhancement up to 10 kW. • The net metering agreement has been incorporated into the application on the National Portal, eliminating the need for a separate physical agreement.• Simplified process for registration of vendors to ensure sufficient and qualified vendors are available.
• Capacity-building and training programs are being conducted to create skilled manpower. • Creating awareness about the scheme through outreach and awareness programs such as print advertising in leading newspapers, TV commercial campaigns, Radio campaigns across FM stations, including regional channels, etc., across the country.
• Regular monitoring of the scheme's progress at different levels, including with states/DISCOMs. • Conducting regional review meetings from time to time. • Established grievance redressal mechanism for timely resolution of grievances. A Call Centre with telephone number 15555 is operational in 12 languages.
Further, MNRE and REC Ltd., as the National Programme Implementing Agency (NPIA), for
PMSG: MBY, work in close coordination with all the DISCOMs, for effective implementation of the scheme. *****Annexure I referred to in reply of parts (a) & (b) of Lok Sabha Starred Question No. 152 to be answered on 29.07.2026 regarding Rooftop Solar Installations under PM-SGMBY RTS capacity-wise and State/UT-wise details of progress made under the PMSG: MBY across the country (As on 24.07.2026) (in Nos.) S. State/UT Installations Households Installations Households Installations Households No. Up to 2 kWp Up to 2 2 – 3 kWp 2 – 3 kWp above 3 above 3 kWp (Greater (Greater kWp kWp than 2 kWp than 2 and upto 3 kWp and kWp) upto 3 kWp) 1 A&NI 2 2 13 13 390 409 2 Andhra 322 323 77349 77352 170145 174386 Pradesh 3 Arunachal 0 0 1 1 Pradesh 4 Assam 365 798 1966 1978 156339 156606 5 Bihar 141 141 1084 1384 22897 23230 6 Chandigarh 41 41 115 115 1212 1212 7 Chhattisgarh 520 760 1731 2233 79598 81324 8 Goa 11 11 26 26 3302 4525 9 Gujarat 13632 14516 53453 56704 696417 1024449 10 Haryana 544 5342 33604 35196 79566 82749 11 Himachal 59 60 174 174 11518 11543 Pradesh 12 J&K 103 104 387 387 38318 38464 13 Jharkhand 13 13 84 84 3145 3366 14 Karnataka 182 906 5086 5625 17581 27836 15 Kerala 263 264 3671 3671 299751 306486 16 Ladakh 2 2 8 8 2005 2005 17 Lakshadweep 0 0 1185 1185 18 Madhya 120 122 7360 7359 147422 152567 Pradesh 19 Maharashtra 3315 4358 37138 37708 647366 1022982 20 Manipur 1 1 24 24 1504 1504 21 Meghalaya 18 18 6 6 37 9282 22 Mizoram 6 6 53 53 1277 1279 23 Nagaland 1 1 28 28 405 405 24 NCT of 46 45 1034 1034 9389 14155 Delhi 25 Odisha 44830 44832 5452 5453 90064 91141 26 Puducherry 31 32 204 204 4490 4560 27 Punjab 227 227 1040 1040 15941 15944 28 Rajasthan 1164 1306 16393 16402 252530 261339 29 Sikkim 4 4 10 10 43 43 30 Tamil Nadu 759 854 11077 11519 73323 88024 31 Telangana 98 144 7502 7502 46630 6181232 DNH&DD 537 537 12 12 570 570 33 Tripura 12 12 367 367 4037 4048 34 Uttar Pradesh 1356 1823 73275 73630 621714 628469 35 Uttarakhand 73 78 707 707 94912 95263 36 West Bengal 59 59 633 633 2337 2440 Total 68,857 77,742 3,41,066 3,48,641 35,97,361 43,95,603Annexure II referred to in reply of parts (a) & (b) of Lok Sabha Starred Question No.
152 to be answered on 29.07.2026 regarding Rooftop Solar Installations under PM- SGMBY RTS capacity-wise and District-wise details of progress made under the PMSG: MBY in the state of Chhattisgarh (As on 24.07.2026) Districts Up to 2 kWp 2-3kWp Above 3kWp (Greater than 2 kWp and upto 3 kWp) s n s d s n s d s n s d o l o l o l i o i o i o t a h t a h t a h l e l e l e l a t s u l a t s u l a t s u s o s o s o n H n H n H I I I Balod 14 14 30 30 1,884 1,884 Balodabazar- Bhatapara 28 28 92 92 5,391 5,391 Balrampur- Ramanujganj 3 3 9 9 319 319 Bastar 15 15 28 28 895 895 Bemetara 32 32 57 57 1,383 1,383 Bijapur 1 1 37 37 Bilaspur 48 48 130 130 5,486 5,698 Dantewada 1 1 1 1 102 102 Dhamtari 18 18 179 179 3,868 3,868 Durg 53 293 231 733 11,959 12,389 Gariyaband 13 13 44 44 1,805 2,015 Gaurella Pendra Marwahi 1 1 12 12 235 235 Janjgir Champa 10 10 36 36 3,071 3,071 Jashpur 2 2 18 18 569 569 Kabeerdham 6 6 10 10 672 672 Kanker 8 8 18 18 1,423 1,423Khairgarh Chhuikhadan Gandai 3 3 15 15 676 676 Kondagaon 9 9 16 16 1,522 1,522 Korba 73 73 69 69 2,036 2,036 Korea 13 13 313 313 Mahasamund 30 30 93 93 4,166 4,166 Manendragarh Chirimiri Bharatpur 3 3 203 203 Mohla Manpur Ambagarh Chouki 1 1 14 14 226 226 Mungeli 15 15 61 61 983 983 Narayanpur 3 3 235 235 Raigarh 6 6 40 40 3,473 3,473 Raipur 90 90 338 338 17,966 18,841 Rajnandgaon 20 20 77 77 4,163 4,163 Sakti 6 6 15 15 654 654 Sarangarh Bilaigarh 9 9 53 53 2,038 2,038 Sukma 2 2 106 106 Surajpur 3 3 6 6 322 322 Surguja 3 3 17 17 1,416 1,416 Total 520 760 1,731 2,233 79,597 81,324Annexure III referred to in reply of parts (c) of Lok Sabha Starred Question No. 152 to be answered on 29.07.2026 regarding Rooftop Solar Installations under PM-SGMBY RTS Capacity-wise and State/UT-wise details of loan applications sanctioned and disbursed under the PMSG: MBY across the country (As on
24.7.2026) Up to2 kWp 2 - 3 kWp Above 3 kWp (Greater than 2 kWp and upto 3 kWp) d dr .o N dr d dr .o N dr d dr .o N dr e n o i t c n.o N e n o i t c nC n i .t m d e s r u e s r u b sC n i .t m e n o i t c n.o N e n o i t c nC n i .t m d e s r u e s r u b sC n i .t m e n o i t c n.o N e n o i t c nC n i .t m d e s r u e s r u b sC n i .t m a S a SA b s i i DA a S a SA b s i i DA a S a SA b s i i DA D D D ANDAMAN 2.22 2.06 13 0.26 11 0.22 AND NICOBAR 5 0 5 0 109 106 ISLANDS ANDHRA 2 ,374.34 2,038.61 18,285 411.10 16,767 349.82 PRADESH 2,607 38 2,259 31 123,782 112,867 ARUNACHAL 0.06 0.02 1 0.04 0 0.00 PRADESH - - - - 3 1 ASSAM 3 ,029.20 2,257.40 8,852 207.26 7,850 160.46 2,469 37 1,950 27 158,374 134,732 BIHAR 2 53.87 190.55 3,592 97.11 3,069 73.99 639 9 469 6 13,577 11,508 CHANDIGARH 0.48 0.23 23 0.54 20 0.42 3 0 - - 27 14 1 , 2 45.70 872.75 8,256 192.77 7,057 145.62 CHHATTISGARH 1,085 14 801 9 67,005 54,021 DELHI 0.00 0.00 0 0.00 0 0.00 - - - - - - GOA 0.23 0.22 735 28.22 662 23.38 - - - - 12 12GUJARAT 1 24.96 103.97 105,695 1,744.64 90,132 1,313.24 323 3 281 3 8,735 7,875 HARYANA 565.06 417.16 7,281 152.77 6,622 118.03 16,635 210 14,472 149 32,173 29,198 HIMACHAL 99.41 75.47 1,041 20.72 912 16.05 PRADESH 54 1 42 1 5,594 4,753 JAMMU AND 3 73.39 302.16 6,276 157.66 5,345 133.18 KASHMIR 175 2 118 2 22,990 18,845 JHARKHAND 24.21 17.51 1,014 26.83 879 20.64 31 0 18 0 1,284 1,043 KARNATAKA 80.34 68.18 2,268 55.99 2,080 46.19 542 8 479 7 4,164 3,820 KERALA 2 , 4 12.96 2,085.88 63,167 1,368.46 58,959 1,151.16 348 6 327 5 124,307 116,970 LADAKH 1.71 1.22 4 0.08 3 0.05 2 0 - - 109 82
7.66 6.83 3 0.06 3 0.06 LAKSHADWEEP 1 0 1 0 511 497 MADHYA 1 , 1 34.29 964.26 30,188 650.85 27,707 538.28 PRADESH 237 4 210 3 61,788 57,046 2 ,180.57 1,854.43 189,417 3,725.12 166,914 2,998.74 MAHARASHTRA 2,464 33 2,106 26 117,701 107,023 MANIPUR 13.08 10.93 229 6.62 214 5.65 19 0 16 0 743 688 MEGHALAYA 0.19 0.19 1 0.04 1 0.04 12 0 11 0 10 10 MIZORAM 0.06 0.04 3 0.07 2 0.04 1 0 - - 3 3 NAGALAND 1.67 1.52 7 0.17 5 0.13 5 0 4 0 88 87 NCT OF DELHI 31.58 22.57 1,112 23.67 989 17.36 42 1 13 0 1,732 1,492 ODISHA 1 ,512.44 1,133.51 2,960 60.65 2,573 47.33 3,895 52 3,213 39 80,279 67,958ODISSA 0.55 0.39 7 0.25 6 0.19 12 0 11 0 29 24 PUDUCHERRY 25.49 21.84 930 19.24 835 15.79 36 1 32 0 1,347 1,242 PUNJAB 43.70 31.77 4,658 100.97 4,237 81.87 121 1 19 0 2,444 2,003 RAJASTHAN 2 , 0 31.00 1,641.37 72,037 1,496.17 65,590 1,181.85 443 6 398 5 112,305 102,391 SIKKIM 0.19 0.16 4 0.13 3 0.08 6 0 3 0 10 10 TAMIL NADU 217.68 184.47 8,387 179.94 7,560 148.92 1,650 22 1,459 18 11,951 10,904 TELANGANA 3 45.21 299.77 9,255 213.76 8,517 181.33 175 3 147 2 17,951 16,629 THE DADRA 0.03 0.02 67 1.20 62 0.92 AND NAGAR - - - - 2 2 HAVELI AND DAMAN AND DIU TRIPURA 46.47 34.76 984 20.51 798 15.31 245 3 183 2 2,477 2,026 UTTAR 7,709.81 5,809.03 44,866 949.72 40,183 750.00 PRADESH 34,704 453 28,732 338 432,845 373,796 1 , 0 04.87 824.09 8,124 175.43 7,489 141.96 UTTARAKHAND 156 2 144 2 53,897 49,565 WEST BENGAL 20.13 13.36 551 11.12 427 7.17 378 5 286 3 1,160 918 Grand Total 2 6,914.83 21,288.69 600,293 12,100.17 534,483 9,685.46 69,520 915 58,209 678 1,461,518 1,290,161Annexure IV referred to in reply of parts (c) of Lok Sabha Starred Question No. 152 to be answered on 29.07.2026 regarding Rooftop Solar Installations under PM-SGMBY RTS capacity-wise and District-wise details of loan applications sanctioned and disbursed under the PMSG: MBY for the state of Chhattisgarh (As on 24.7.2026) District Name Up to 2 kWp 2-3 kWp Above 3 kWp (Greater than 2 kWp and upto 3 kWp) d dr .o N dr d dr .o N dr d dr .o N dr e n o i t c n.o N e n o i t c nC n i .t m d e s r u e s r u b sC n i .t m e n o i t c n.o N e n o i t c nC n i .t m d e s r u e s r u b sC n i .t m e n o i t c n.o N e n o i t c nC n i .t m d e s r u e s r u b sC n i .t m a S a SA b s i i DA a S a SA b s i i DA a S a SA b s i i DA D D D BALOD 3 3 . 3 1 2 2 . 7 7 96 2.35 83 1.74 17 0.23 16 0.20 1,802 1,374 BALODA BAZAR 0 . 5 8 0 . 5 3 12 0.33 11 0.29 1 0.02 1 0.02 32 30 BALODABAZAR- 1 0 2 . 5 1 7 6 . 0 5 568 11.59 510 8.91 BHATAPARA 52 0.72 42 0.52 5,499 4,683 BALRAMPUR 0 . 0 0 0 . 0 0 0 0.00 0 0.00 - - - - - - BALRAMPUR- 5 . 6 0 4 . 1 6 24 0.64 21 0.54 RAMANUJGANJ 2 0.02 2 0.01 292 238 BASTAR 1 5 . 7 0 1 1 . 2 3 107 2.64 74 1.66 29 0.37 21 0.23 820 668 BEMETARA 2 6 . 2 0 1 6 . 4 5 92 1.99 79 1.48 30 0.36 17 0.18 1,412 1,016 BIJAPUR 0 . 9 8 0 . 5 7 17 0.72 14 0.43 3 0.04 1 0.01 52 41 BILASPUR 6 5 . 6 8 4 5 . 9 0 658 16.32 578 12.56 75 0.89 63 0.65 3,557 2,886DAKSHIN 2 . 1 1 1 . 5 1 32 0.92 30 0.72 BASTAR 2 0.02 1 0.01 111 93 DANTEWADA DANTEWADA 0 . 3 7 0 . 2 6 6 0.20 5 0.12 1 0.02 1 0.01 18 14 DHAMTARI 6 7 . 9 9 4 4 . 3 9 272 6.11 209 4.18 89 1.12 67 0.74 3,652 2,758 DURG 138.23 1 00.84 1,720 38.38 1,534 30.92 118 1.27 75 0.78 7,503 6,252 GARIYABAND 38.46 27.07 50 1.27 43 0.97 44 0.63 30 0.34 2,046 1,671 GAURELLA 4.15 2 .69 21 0.60 18 0.44 PENDRA 9 0.12 6 0.08 222 172 MARWAHI JANJGIR 50.10 37.59 262 6.07 233 4.84 CHAMPA 27 0.34 18 0.21 2,726 2,313 JASHPUR 1 2.77 8 .32 50 1.26 43 0.92 16 0.22 12 0.13 677 523 KABEERDHAM 1 3.61 9 .46 44 1.07 35 0.76 7 0.09 6 0.07 733 580 KABIRDHAM 0 . 0 9 0 . 0 4 0 0.00 0 0.00 2 0.03 1 0.02 5 3 KANKER 2.49 1 .69 17 0.43 13 0.29 3 0.04 3 0.04 134 107 KHAIRGARH 1 2.80 6 .47 32 0.72 22 0.40 CHHUIKHADAN 14 0.20 8 0.10 695 435 GANDAI KONDAGAON 45.60 26.10 143 3.88 81 2.02 15 0.19 13 0.14 2,388 1,521 KORBA 29.54 22.30 192 4.87 176 4.04 54 0.68 48 0.52 1,597 1,373KOREA 5.37 4 .14 22 0.48 18 0.34 9 0.13 5 0.07 288 248 KORIYA 0 . 0 7 0 . 0 4 0 0.00 0 0.00 - - - - 4 3 MAHASAMUND 75.73 57.34 239 5.67 203 4.11 62 0.83 46 0.54 4,064 3,537
3.42 2 .79 28 0.66 26 0.53 MANENDRAGAR 3 0.04 3 0.04 181 167 H CHIRIMIRI BHARATPUR MOHLA 3.29 1 .64 15 0.32 9 0.18 MANPUR 2 0.03 1 0.01 180 105 AMBAGARH CHOUKI MUNGELI 19.39 1 2 .61 85 2.15 71 1.51 81 1.02 47 0.49 1,043 797 NARAYANPUR 4.51 3 .32 29 0.81 27 0.69 1 0.01 1 0.01 237 189 RAIGARH 66.37 49.47 407 10.56 362 8.49 22 0.30 16 0.20 3,579 3,010 RAIPUR 231.75 161.83 2,214 51.13 1,880 38.18 168 2.07 145 1.53 12,444 10,230 RAJNANDGAON 68.70 44.11 411 9.19 334 6.66 44 0.57 29 0.34 3,743 2,728 SAKTI 8.71 6 .15 47 1.12 41 0.88 4 0.06 4 0.05 474 386 SARANGARH 34.78 26.60 67 1.66 64 1.36 BILAIGARH 44 0.58 33 0.36 1,865 1,635 SUKMA 2.31 1 .63 15 0.38 13 0.30 - - - - 124 100 SURAJPUR 4.95 3 .48 34 0.88 16 0.42 4 0.05 2 0.02 263 213SURGUJA 1 5.92 1 0 .36 100 2.45 70 1.50 10 0.14 3 0.03 864 627 0 . 0 9 0 . 0 5 1 0.03 1 0.02 THIRUVANNAM - - - - 5 3 ALAI UTTAR BASTAR 1 6 7 4 31.45 1292 20.79 127 2.94 110 2.24 KANKER 21 0.29 14 0.17 Total 1,085 14 801 9 67,005 1,245.70 54,021 872.75 8,256.00 192.77 7,057.00 145.62Annexure V referred to in reply of parts (d) of Lok Sabha Starred Question No. 152 to be answered on 29.07.2026 regarding Rooftop Solar Installations under PM-SGMBY State/UT-wise details of beneficiaries reported by DISCOMs to receive zero electricity bill after
installation of RTS systems under the PMSG: MBY across the country (As on 20.07.2026) S. No. Name of States/UTs DISCOM Number of Consumers whose energy charges are zero during any month/billing period (Nos.)
1. A&N ISLANDS Electricity Deptt. of Andaman & Nicobar 139 Islands
2. ANDHRA PRADESH Central Power Distribution Corporation of 16,584 A.P. Ltd.
3. Southern Power Distribution Company of AP 18,891 Limited
4. Eastern Power Distribution Company of A P 30,372 Ltd
5. ASSAM Assam Power Distribution Company Limited 72,593
6. BIHAR North Bihar Power Distribution Company 1,774 Limited
7. South Bihar Power Distribution Company 3,858 Limited
8. CHANDIGARH Chandigarh Power Distribution Limited 358
9. CHHATTISGARH Chhattisgarh State Power Distribution 16,450 Company Limited
10. TEED 22
11. GOA Electricity Deptt. of Goa 1,143
12. GUJARAT Paschim Gujarat Vij Co. Limited 1,44,720
13. Torrent Power Limited - Ahmedabad 48,942
14. Madhya Gujarat VIJ Company Ltd. 65,549
15. Dakshin Gujarat Vij Co.Ltd (DGVCL) 70,774
16. Uttar Gujarat Vij Company Limited 76,543
17. Torrent Power Limited - Surat 9829
18. HARYANA Uttar Haryana Bijli Vitran Nigam Limited 22,184
19. Dakshin Haryana Bijli Vitran Nigam Limited 10,665
20. HIMACHAL Himachal Pradesh State Electricity Board Ltd 7,315 PRADESH
21. J&K JPDCL 4,128
22. KPDCL 4,545
23. JHARKHAND TATA STEEL UTILITIES AND 7 INFRASTRUCTURE SERVICES LIMITED
24. Tata Steel Limited 9
25. Jharkhand Bijli Vitran Nigam Limited 344
26. KARNATAKA Mangalore Electricity Supply Company 348 Limited
27. Chamundeshwari Electricity Supply Company 350 Ltd. (CHESCOM),
28. Hubli Electricity Supply Company Ltd. 560
(HESCOM)29. Bangalore Electricity Supply Company Ltd. 4507
(BESCOM)
30. Gulbarga Electricity Supply Company Ltd. 303
(GESCOM)
31. KERALA Kerala State Electricity Board 1,91,882
32. Thrissur Corporation 593
33. LADAKH Ladakh Power Development Department 7,983
34. LAKSHADWEEP Electricity Deptt. of Lakshadweep 4,966
35. MADHYA M.P.Madhya Kshetra Vidyut Vitran Co. 40,779
36. PRADESH M.P.Paschim Kshetra Vidyut Vitran Co. 45,480
37. M.P. Poorv Kshetra Vidyut Vitran Co 24,253
38. MAHARASHTRA Maharashtra State Electricity Distribution Co. 4,17,707 Ltd
39. Brihanmumbai Electric Supply & Transport 26
(BEST)
40. Tata Power Co. Ltd 103
41. Adani Electricity Mumbai Limited 266
42. NIDAR UTILITIES PANVEL LLP 3
43. MANIPUR Manipur State Power Distribution Company 351 Limited (MSPDCL)
44. MEGHALAYA Meghalaya Power Distribution Corporation 10 Ltd.
45. MIZORAM Power & Electricity Department, Government 156 of Mizoram
46. NAGALAND Department of Power, Nagaland 200
47. NCT OF DELHI Tata Power DDL 774
48. BSES Rajdhani Power Limited 756
49. BSES Yamuna Power Limited 481
50. NEW DELHI MUNICIPAL COUNCIL
51. ODISHA TPNODL, TP Northern Odisha Distribution 6,302 Limited
52. TPWODL, TP Western Odisha Distribution 10,885 Limited
53. TPCODL, TP Central Odisha Distribution Ltd. 16,414
54. TPSODL, TP Southern Odisha Distribution 4,077 Limited
55. PUDUCHERRY Electricity Department, Puducherry 2,813
56. PUNJAB Punjab State Power Corporation Ltd. 12,939
57. RAJASTHAN Jodhpur Vidyut Vitran Nigam Ltd. 54,611
58. Jaipur Vidyut Vitran Nigam Ltd. 52,979
59. Ajmer Vidyut Vitran Nigam Ltd. 60,511
60. SIKKIM Energy & Power Department, Government of 2 Sikkim
61. TAMIL NADU Tamil Nadu Generation and Distribution 49,747 Company Limited
62. TELANGANA Southern Power Distribution Company of 9,115 Telangana Limited
63. Northern Power Distribution Company of 13,561 Telangana Limited64. Co-operative Electric Supply Society(CESS) 145
65. THE D&NH AND Electricity Deptt. of Dadar & Nagar Haveli 321 D&D
66. TRIPURA Tripura State Electricity Corporation Limited 2,681
67. UTTAR PRADESH Madhyanchal Vidyut Vitran Nigam Ltd 81,593
(MVVNL)
68. Noida Power Company Limited 943
69. Poorvanchal Vidyut Vitran Nigam 38,160 Ltd.
70. Dakshinanchal Vidyut Vitran Nigam 21,627 Ltd.
71. Torrent Power Limited 7,343
72. Pashchimanchal Vidyut Vitran Nigam 17,419 Ltd. (PVVNL)
73. Kanpur Electric Supply Company Ltd. 8,006
74. UTTARAKHAND Uttarakhand Power Corporation Ltd 50,715
75. WEST BENGAL CESC 510 Total 18,93,994 *****